High School Renovation

myMTLSD
Dashboard
MTLSDHome
Email Access
PowerTeacher
Public Folders
Site Administration
SubFinder
MyPDC
School Messenger

District Home
Renovation Home
About the Project
BoardPresidentFAQ
FAQs
Act 34 Hearing
Schematic Design
Project Financing
Project Updates
Renovation Blog
About the High School
Meetings
Video Archive
HS Project Documents
Community Forums
Community Advisory Committee
DeJong Study
HS Project Process
Architects
Construction Manager
Contact Us

Login

 

High School Renovation Process

The process for the renovation of Mt. Lebanon High School formally began in the summer of 2006.  At that time, it was decided that an education specification team would be assembled for the purpose of identifying key needs related to the future use of a high school building.  The team consisted of a variety of stakeholders who met for several work sessions during the fall and early winter.  The team was led by William DeJong & Associates.  The results of their work, including both general and specific suggestions, were presented to the Board of School Directors in January of 2007. 

Since then, the essential milestones with associated activities related to updating a high school building have been identified.  Necessary outcomes from each phase (milestone) have been identified to monitor the progress of the project.  Due to the complexity of a building project, it is acknowledged that only major milestones, activities, and outcomes have been listed. The shaded areas indicate completed activities related to the project.

 

 

 
Phase #1: Need Study & Project Conception

 Status

 Activity

 Outcome

 
 1. Feasibility    Studies  Educational Studies & Reports

 Completed

 2. Site Analysis

  Recommendations

 Completed

 3. Programming

 Budget, schedules & community involvement 

 Completed

 

 
Phase # 2: Design

 

 Activity

  Outcome

 

 1. Architect solicited and selected
-PDE Requirements
-Concepts Prepared
-Site survey

 Proposals, presentations & site visits
 Architects: Celli-Flynn Brennan (Pittsburgh); OWP/P (Chicago)
-Plan Con "A" initiated
-Topograhic and property survey
-Concepts prepared and presented to School Board

 Completed

 Completed
 Completed
 Ongoing

 2. Community Engagement

Community and stakeholder involvement: Design Advisory Team meetings, High School staff meetings held with architects; July 22, 2008 Community Forum; monthly Architect Updates one hour prior to monthly School Board Discussion Meeting.  Upcoming community meetings: January 14, 20, 21, 22, 2009.  Ongoing
3. Construction Manager Selected P. J. Dick Incorporated was selected as Construction Manager to oversee design and develop cost estimates, project schedule, prepare constructability review and value engineering.

 Completed

4. Schematic Design


Community and stakeholder involvement, renderings, schematic drawings, preliminary project descriptions,site selections, modifications, geotechnical data, project phasing, preliminary cost projections & continuation of Plan Con Process.

 Ongoing
 5.Design Development Select construction option, LEED certification consideration, financing options, drawings, plans, elevations, sections, typical details, outline specifications, engineering criteria, storm water management, develop phasing schedule, select construction management option, revised cost projections, permitting and zoning, environmental health & furniture and salvage.  
6. Financing  Early funding of architect and construction management fees.  
 


 Phase #3: Construction Documentation

 

Activity

  Outcome

 
  1. Construction Documents Detailed drawings, final elevations, sections and details, revised schedule, instructions to bidders, bid forms and requirements, general and supplementary conditions, revised cost projections & labor and Industry approval.  
 

 
Phase # 4: Bidding/Negotiations

 

Activity

Outcome

 
1. Competitive Bidding  Request for bids, addenda, bids, bid security & non collusion affidavit  
 2. Direct Purchase of Materials  Purchase orders  
 3. Review and Award Contract Agreement  
4. Financing  Bond issuance and budgets approved. Process for change order approval developed  
 


 Phase # 5: Construction

 

 Activity

Outcome

 
  1. Mobilization  Bonds, insurance, permits, schedules, traffic control plan & lay down areas  
 2. Construction & Construction Management Shop drawings, construction management documents, inspections, progress reports, change orders, field orders, payroll certifications & Plan Con Documents  
 3. Project close out Substantial completion, punch lists, record documents, warranties, operation and maintenance data, final inspection & commissioning  
 4. Financing  Payment process developed and implemented  
 


 Phase#6: Facility Management

 

 Activity

 Outcome

 
 1. Occupancy  Moving  
 2. Operation and Maintenance  Maintenance schedules and records, repairs & staffing  
 3. Post Occupancy Analysis  Evaluation reports & warranty service reports  
 


 Phase #7: Total Project Completion

 

 Activity

Outcome

 
 1. Building Dedication   Occupancy Certificates & building dedication  
  2. Facility Use  Wear out/attrition of materials and equipment & building retirement  
  3. Financing  Reconciliation of bond funds to total project cost  

Print Page