Progress Continues with High School Construction
July 29, 2012
 |
| Construction along Horsman Drive at the back of the high school. |
Construction at the high school continues to make progress during the summer months. With the exception of a few rainy days, the weather has cooperated to help keep the project on track. Work on the new science wing, athletic field house, loading dock and South parking lot is in full force.
Last week, the contractors continued to work in the following areas: -Forming walls at the loading dock -Asbestos abatement in 5-B and F buildings -Installing steel deck on upper “J” framing -Installing storm sewers in South parking lot -Demolishing walls on 6-B classrooms -Pouring concrete walls in “G” north and “G” south
Work will continue in the the following areas next week: -Pouring of concrete walls at the loading dock -Construction of curbs and storm sewers in south parking lot -Back filling inside “H” building -Pouring concrete walls in “G” south -Completion of the asbestos abatement on 5-B -Begin to install mechanical and electrical items in 6-B -Removing and re-setting the roof coping on “B” building
|