Mt. Lebanon High School Construction/Renovation Project

*** High School Traffic Patterns and  Parking Locations***

Monthly updates on the progress of the high school project are given by the construction managers at 7:00 p.m. on the second Monday each month before the School Board Discussion meeting in the Jefferson Middle School Library.

Slideshow of  Finished Spaces in the High School 

March 2015 High School Project Photos


Construction Updates
       

 



New Center Court.

 








April 7, 2015 Construction Update

Construction Update PowerPoint April 7, 2015

Upcoming work:

  • Horsman Drive - site curbs, regrading and paving
  • D South Courtyard – Start site walls, concrete stairs
  • D North Courtyard – Completion of Metal panels
  • 1D –Family and Consumer Science Countertops, appliances, cabinet completion
  • A and C Buildings – Abatement contractor has mobilized.  Containment and isolation areas are being constructed.
  • A Building Demolition – Late May 2015 Start
     Building Key:  
    A- Existing Boiler rooms and North Gym
    B- Cochran Road Building (academic wing)
    C- Academic and administration
    D- Existing Gymnasium
    E- Auditorium
    F- Fine Arts
    G- New Science Building
    H- New Aux. Gyms
    J- New Main competition Gym